Decision Memo Completed

GMP Silver Lake Diversion Dam Dredging

Green Mountain and Finger Lakes National Forests Addison, Vermont Middlebury Ranger District

Application to authorize improvement of the Silver Lake and Sucker Brook Diversion Dam access roads, installation of temporary structures to allow for removal of accumulated sediment from impoundment, and deposition of the sediment at the Goshen Pit.

Location

Town of Goshen

Project timeline

1
Scoping Start
06/03/2024
2
Decision
08/2024 (Estimated)
3
Implementation
08/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
GMP Silver Lake Diversion Dam DredgingDecision Signed Date: 08/22/2024
ForestsGreen Mountain And Finger Lakes National Forests
DistrictsMiddlebury Ranger District
Legal Land DescriptionNot Applicable
Special use management