Application for Special Use Permit to erect wind turbines and develop a commercial wind power facility on National Forest lands. Supplemental DEIS released in late December 2010; FEIS/ROD released in January, 2012.
Location
Green Mountain National Forest, Towns of Readsboro and Searsburg
Project timeline
1
NOI in Federal Register
07/15/2005
2
DEIS NOA in Federal Register
12/23/2010
3
FEIS NOA in Federal Register
01/06/2012
4
Decision
01/2012 (Estimated)
5
Implementation
06/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Deerfield Wind Project | Decision Signed Date: 01/03/2012 Legal Notice Date: 01/10/2012 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |