Decision Memo Completed

Great Lakes Gas Transmission O&M Plan

Hiawatha National Forest Delta; Schoolcraft, Michigan Rapid River Ranger District

Create a new Operation and Maintenance Plan as called for in their special use permit.

Location

This project is located between FH-13 and M-94

Project timeline

1
Scoping Start
02/23/2005
2
Decision
10/2009 (Estimated)
3
Implementation
02/2011 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Great Lakes Transmission Limited Partnership Pipeline O & M Plan DMDecision Signed Date: 10/15/2009
ForestsHiawatha National Forest
DistrictsRapid River Ranger District; Manistique Ranger District
Legal Land DescriptionT44N, R18W, Sections 12, 13, 24, 30 & 36
Special use management