Issue an amendment to the Chatham Telephone Company SUP for installation of a fiber optic cable crossing National Forest land. The cable will be buried in a road ROW following existing telephone corridor. No vegetation will be removed.
Location
Corridor is located on the Westside of the Hiawatha National Forest
Project timeline
1
Scoping Start
10/22/2010
2
Decision
01/2011 (Estimated)
3
Implementation
04/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Chatham Telephone Company Fiber Optic Cable Installation Decision Memo | Decision Signed Date: 01/20/2011 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District |