Commercial thin 3,704 ac. of red pine. Under plant white pine on 1,205 ac. Underburn 410 ac. of red pine stands. Construct about 1.4 mi. of new roads. Reinforce 15 existing road closures.
Location
Throughout the Eastside of the Hiawatha National Forest.
Project timeline
1
Scoping Start
09/27/2013
2
Comment Period
02/27/2015
3
Objection Period Start
06/29/2015
4
Decision
11/2015 (Estimated)
5
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Special Area Management; Travel Management; Timber Sales (Green) |
| East Red Pine 3 | Decision Signed Date: 11/17/2015 |
| Forests | Hiawatha National Forest |
| Districts | Sault Ste. Marie Ranger District; St. Ignace Ranger District |
| Legal Land Description | Not Applicable |