Installation of 1,980 feet of powerline in the County Road KK road right-of-way. The line would feed power to an Enbridge Energy pipeline emergency shut-off valve.
Location
Westside of the Hiawatha National Forest
Project timeline
1
Scoping Start
05/16/2011
2
Decision
10/2011 (Estimated)
3
Implementation
12/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Alger Delta Cooperative Electric Association County Road KK powerline | Decision Signed Date: 10/31/2011 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District |
| Legal Land Description | T41N, R19W, Sections 14 and 23 |