Install 2,600 feet of buried powerline within the M-123 road right-of-way.
Location
Eastside of the Hiawatha National Forest in Chippewa County
Project timeline
1
Scoping Start
04/27/2011
2
Decision
06/2011 (Estimated)
3
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Cloverland Electric M-123 Line Installation | Decision Signed Date: 06/10/2011 |
| Forests | Hiawatha National Forest |
| Districts | Sault Ste. Marie Ranger District |
| Legal Land Description | T46N, R6W, Section 35 |