To issue a special use permit to Enbridge Pipelines for the excavation, inspection, and repair of their Line 5 petroleum/natural gas liquids pipeline at two sites near the Sturgeon River, just east of Forest Highway 13.
Location
Approximately 3 miles north of US 2 at Nahma Junction, along FH13, just north of Flowing Well Campground. Access to the work area would be along the pipeline easement approx. 1/4 mile east of FH13.
Project timeline
1
Scoping Start
05/18/2012
2
Comment Period
12/21/2012
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Enbridge Line 5 Pipeline Inspection and Maintenance Project | Decision Signed Date: 08/14/2013 Legal Notice Date: 08/19/2013 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District |
| Legal Land Description | T41N, R19W, Section 20 NE |