The project consists of expansion of the parking lot at Valley Spur Trailhead, construction of a garage to house ski trail grooming equipment, installing a yurt, replacing toilet building.
Location
Valley Spur trailhead is 8 miles southwest of Munising, MI.
Project timeline
1
Scoping Start
05/18/2015
2
Decision
04/2016 (Estimated)
3
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Trail Management; Road Improvements/Construction |
| Valley Spur Trailhead Improvements | Decision Signed Date: 04/07/2016 |
| Forests | Hiawatha National Forest |
| Districts | Munising Ranger District |
| Legal Land Description | T46N R19W Section 20 |