Re-issue Special Use Permit to include: All existing distribution lines and Rights of Way within HNF lands, Electric substations at Eckerman and Raco locations.
Location
Distribution line Rights of Way located across Eastside of HNF (Mackinac & Chippewa Counties) and a small portion of Manistique Ranger District (Delta County)
Project timeline
1
Scoping Start
05/31/2013
2
Comment Period
05/31/2013
3
Decision
11/2013 (Estimated)
4
Implementation
12/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| 2013 Cloverland Electric Special Use Permit Re-issue | Decision Signed Date: 11/20/2013 Legal Notice Date: 12/11/2013 |
| Forests | Hiawatha National Forest |
| Districts | Hiawatha National Forest All Units |
| Legal Land Description | Not Applicable |