Decision Memo Completed

Alger Delta Permit Amendment

Hiawatha National Forest Alger, Michigan Hiawatha National Forest All Units

Permit Amendment to authorize installing a buried cable at a depth of 48 inches within a permitted road to provide power to existing structures on private land. The action would begin at an existing permitted power pole and extend about 600 feet.

Location

T 45 N, R 19 W, Section 28

Project timeline

1
Scoping Start
07/26/2013
2
Decision
02/2014 (Estimated)
3
Implementation
02/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Alger Delta Permit AmendmentDecision Signed Date: 02/03/2014 Legal Notice Date: 02/05/2014
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionTownship 45 N, Range 19 W, Section 28