Within existing corridor, Enbridge Energy LP proposes to exacavate section of pipeline to install emergency flow restriction device, install valve control building and communication pole with gravel and fence around, and construct gravel access road.
Location
Northeast of Rapid River, Michigan, on the east side of County Road 509
Project timeline
1
Scoping Start
08/15/2014
2
Decision
06/2015 (Estimated)
3
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Oil |
| Enbridge 1359 Site and Road Construction | Decision Signed Date: 06/30/2015 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District; Manistique Ranger District |
| Legal Land Description | T 41 N, R 21 W, SE 1/4 of SE 1/4 of Section 15 |