Decision Memo Completed

Upper Peninsula Power Company Underground Electric Cable Installation

Hiawatha National Forest Delta, Michigan Hiawatha National Forest All Units

Install over 10000 feet of underground electric cable to power the Enbridge 1359 Site. Install 4 junction enclosures and one transformer.

Location

In the right-of-way on the west of County 509 Y Road, from 26.6 Road north to the Enbridge pipeline, then east along the south edge of the pipeline easement for approximately 200 feet.

Project timeline

1
Scoping Start
08/29/2014
2
Decision
12/2014 (Estimated)
3
Implementation
04/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Upper Peninsula Power Company Underground Electric Cable InstallationDecision Signed Date: 12/05/2014
ForestsHiawatha National Forest
DistrictsRapid River Ranger District; Manistique Ranger District
Legal Land DescriptionT 41 N, R 21 W, Sections 15, 22, and 27.