Alger Delta Coop proposes installing 3,798 feet of electric cable underground from County Road 513 west along the south side of Twin Springs Road (20.5 Lane).
Location
The project area is approximately 6 miles south of Rapid River, Michigan, on the Stonington Peninsula. From County Road 513 west along the south side of Twin Springs Road (20.5 Lane).
Project timeline
1
Scoping Start
08/25/2014
2
Decision
12/2014 (Estimated)
3
Implementation
12/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Alger Delta Cable Installation | Decision Signed Date: 12/05/2014 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District; Manistique Ranger District |
| Legal Land Description | T 40 N, R 22 W, Section 26 |