Decision Memo Completed

Enbridge Energy Limited Partnership, Pipeline O & M Plan

Hiawatha National Forest Delta; Mackinac; Schoolcraft, Michigan Hiawatha National Forest All Units

Develop an operation and maintenance (O & M) plan for the Enbridge Energy Limited Partnership ROW.

Location

Enbridge Energy Limited has its own corridor that runs through Rapid River, Manistique, St. Ignace Ranger Districts

Project timeline

1
Scoping Start
09/08/2005
2
Decision
01/2010 (Estimated)
3
Implementation
01/2011 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Enbridge Energy Limited Partnership, Pipeline O & M PlanDecision Signed Date: 01/11/2010
ForestsHiawatha National Forest
DistrictsRapid River Ranger District; Manistique Ranger District; St. Ignace Ranger District
Special use management