The Hiawatha Telephone Company is requesting the installation of additional Fiber Optic lines, hand holes, and a remote site.
Location
T42N R18W Sections 5, 7, 8, 18, & 19, T47N R5W Sections 13, 14, & 15, T47N R4W Sections 18, 19, 20, 23, 24, 27, 28, & 29, T46N R4W Sections 23, 26, & 34, T45N R4W Sections 4 & 9
Project timeline
1
Scoping Start
09/13/2018
2
Decision
09/2018 (Estimated)
3
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Hiawatha Telecom Fiber Optic Installation | Decision Signed Date: 09/26/2018 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District; Manistique Ranger District; Sault Ste. Marie Ranger District |
| Legal Land Description | Not Applicable |