Install fiber optic cable underground within the M-28 corridor from Eckerman Corners area to Raco area.
Location
Within the M-28 corridor from the Eckerman Corners area to the Raco area
Project timeline
1
Scoping Start
08/27/2019
2
Decision
09/2019 (Estimated)
3
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Charter Communications M-28 Fiber Optic Installation | Decision Signed Date: 09/17/2019 |
| Forests | Hiawatha National Forest |
| Districts | Sault Ste. Marie Ranger District |
| Legal Land Description | Not Applicable |