Replace foot bridges along the North Country Trail crossing Taylor Creek and North Branch Carp River. Less than 1 mile of trail relocation to meet up with the new bridges.
Location
T43N R4W section 30, and T43N R5W section 35
Project timeline
1
Scoping Start
03/01/2021
2
Decision
03/2021 (Estimated)
3
Implementation
05/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Taylor Creek and North Branch Carp River Bridge Replacement | Decision Signed Date: 03/22/2021 |
| Forests | Hiawatha National Forest |
| Districts | St. Ignace Ranger District |