Fill would be added to low or uneven spots along the trail, replacement of current puncheon, and construction of new puncheon.
Location
This project area includes a section of the North Country Trail starting at Naomikong Overlook traveling north and west toward Naomikong Creek suspension bridge.
Project timeline
1
Scoping Start
09/03/2021
2
Decision
12/2021 (Estimated)
3
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| North Country Trail Naomikong Area Maintenance | Decision Signed Date: 12/15/2021 |
| Forests | Hiawatha National Forest |
| Districts | Sault Ste. Marie Ranger District |
| Legal Land Description | Not Applicable |