Decommissioning of the Moran Work Center
Location
Moran Work Center
Project timeline
1
Scoping Start
06/01/2021
2
Decision
06/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Moran Workcenter Decomissioning | Decision Signed Date: 06/10/2021 |
| Forests | Hiawatha National Forest |
| Districts | St. Ignace Ranger District |
| Legal Land Description | Not Applicable |