Decision Memo Completed

Grand Island Cabin Access & Disposal Project

Hiawatha National Forest Alger, Michigan Munising Ranger District

Removal of three cabins and associated structures on Grand Island National Recreation Area, in addition to making road access improvements.

Location

Project activities would occur within the area known as the "thumb" of the island.

Project timeline

1
Scoping Start
01/10/2024
2
Decision
06/2024 (Estimated)
3
Implementation
08/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Road Improvements/Construction; Special Area Management
Grand Island Cabin Access & Disposal ProjectDecision Signed Date: 06/14/2024
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionNot Applicable
Special area management