Placement of approximately 1,125 ft of underground 7.2kV electric distribution cable due to existing cable reaching end of life and experiencing multiple faults creating outages to the Hiawatha Slopes/Chatham Ski Hill Recreation Area.
Location
Hiawatha Slopes/Chatham Ski Hill
Project timeline
1
Scoping Start
12/22/2023
2
Decision
04/2024 (Estimated)
3
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Hiawatha Slopes Electrical Upgrade | Decision Signed Date: 04/22/2024 |
| Forests | Hiawatha National Forest |
| Districts | Munising Ranger District |
| Legal Land Description | Rock River Township, T46N, R21W, sec 25 |