This line has reached end of life conditions, has failed beyond repair, and needs replacement as quickly as possible to limit recreational impacts on concessionaire campground hosts, services, and recreators.
Location
Bay Furnace Campground
Project timeline
1
Scoping Start
04/30/2025
2
Decision
05/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| UPPCO Amendment 12 - Bay Furnace Campground Powerline Replacement | Decision Signed Date: 05/01/2025 |
| Forests | Hiawatha National Forest |
| Districts | Munising Ranger District |
| Legal Land Description | Not Applicable |