Issue a right-of-way permit to Orange County REMC to trench and place approximately 3,500 feet of new buried powerline along County Road 750 South.
Location
Along County Road 750 South in Orange County, Indiana
Project timeline
1
Scoping Start
11/16/2011
2
Decision
01/2012 (Estimated)
3
Implementation
01/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Orange County REMC - Apple’s Chapel | Decision Signed Date: 01/10/2012 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | T 1 S, R 1 W. Sections 2 and 3 |