Proposal to implement the 2006 Land and Resource Management Plan by increasing the amount of early successional habitat available.
Location
The project is located near Birdseye, Indiana. The project is south of State Road 64, west of State Road 37 and north of Oak Hill Road.
Project timeline
1
Scoping Start
04/21/2014
2
Comment Period
11/02/2015
3
Objection Period Start
02/29/2016
4
Decision
08/2016 (Estimated)
5
Implementation
08/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green) |
| Uniontown North Restoration | Decision Signed Date: 08/10/2016 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | Not Applicable |