Decision Memo Completed

Hoosier Energy Temporary Permit

Hoosier National Forest Orange, Indiana Hoosier National Forest All Units

Proposal to provide Hoosier Energy access to their transmission line for structure/pole replacement.

Location

One location (T1S, R1W, Section 10) is approximately 9 miles southeast of French Lick, IN and the other location (T1S, R1W, Section 27) is approximately 5 miles northwest of English, IN.

Project timeline

1
Scoping Start
10/20/2014
2
Decision
12/2014 (Estimated)
3
Implementation
01/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Hoosier EnergyDecision Signed Date: 12/17/2014
ForestsHoosier National Forest
DistrictsTell City Ranger District
Legal Land DescriptionT1S, R1W, Sections 10 and 27