The Hoosier is proposing to reroute approximately 550 feet of the German Ridge North Loop trail.
Location
The north section of the North Loop of the German Ridge Multiple Use Trail.
Project timeline
1
Scoping Start
01/20/2015
2
Decision
11/2015 (Estimated)
3
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| German Ridge North Loop Reroute | Decision Signed Date: 11/18/2015 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | T6S, R2W, Sections 14 and 15 |