The Hoosier National Forest is proposing to armor the streambank of an intermittent stream with native rock to reduce erosion risk near the Initial Point monument.
Location
Initial Point monument, approximately 1/2 mile southwest of Pine Valley, IN.
Project timeline
1
Scoping Start
05/11/2020
2
Decision
06/2020 (Estimated)
3
Implementation
08/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Heritage Resource Management; Watershed Improvements |
| Initial Point Armoring | Decision Signed Date: 06/08/2020 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |