The Hoosier is proposing to issue Perry-Spencer R.T.C.,Inc. a special use authorization to install approximately 5.8 miles of buried fiber optic cable along county roads in an effort to expand highspeed internet access to residents of rural Perry Co.
Location
The project area covers portions of several Townships/Ranges throughout southern Perry county.
Project timeline
1
Scoping Start
02/01/2021
2
Decision
05/2021 (Estimated)
3
Implementation
05/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Perry Spencer RTC Special Use Permit | Decision Signed Date: 05/07/2021 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | Not Applicable |