The Hoosier is proposing to issue a special use permit amendment to Southern Indiana Power to install and maintain approximately 581 feet of buried electrical line in the Tipsaw Lake Recreation Area.
Location
Tipsaw Lake Recreation Area
Project timeline
1
Scoping Start
07/08/2021
2
Decision
09/2021 (Estimated)
3
Implementation
09/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Southern Indiana Power Permit Amendment | Decision Signed Date: 09/03/2021 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | Township 4 South, Range 2 West, Section 29 |