The Hoosier is proposing a permit amendment to move an existing waterline along State Road 62 in Crawford County, Indiana to accommodate a road repair project by the Indiana Department of Transportation.
Location
Approximately 2 miles west northwest of Sulphur, IN.
Project timeline
1
Scoping Start
11/09/2021
2
Decision
12/2021 (Estimated)
3
Implementation
01/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Patoka Lake Regional Water & Sewer District (PLRWSD) Water Pipeline Relocation | Decision Signed Date: 12/03/2021 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | Township 3 South, Range 1 west, Section 27 |