The Hoosier is proposing to amend the existing permit to extend high speed fiber optic services. This fiber optic line would be buried and installed in the same corridor as an existing and permitted buried electric line.
Location
Approximately 2.5 miles north, northwest of Freetown, IN.
Project timeline
1
Scoping Start
08/15/2023
2
Decision
11/2023 (Estimated)
3
Implementation
11/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Hoosier National Forest |
| Districts | Brownstown Ranger District |
| Legal Land Description | Township 7 N, Range 3 E, Section 25 |