Change name to "Tawas New Dawn KW". Creation of apx.1,370 acres of Kirtland's warbler habitat by a combination of timber harvest, site preparation by mechanical or prescribed fire and tree planting to jack pine. Manage road systems as appropriate.
Location
Three KW units near Iargo, Trout, and Webb Roads intersections.
Project timeline
1
Scoping Start
02/01/2010
2
Comment Period
12/21/2011
3
Decision
02/2012 (Estimated)
4
Implementation
02/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Timber Sales (Green) |
| Tawas New Dawn Decision Notice and Finding of No Significant Impacts | Decision Signed Date: 02/23/2012 Legal Notice Date: 02/28/2012 |
| DN and FONSI for the Tawas New Dawn Kirtland | Decision Signed Date: 02/23/2012 Legal Notice Date: 02/29/2012 |
| Forests | Huron-Manistee National Forest |
| Districts | Huron Shores Ranger District |