To create and enhance wildlife habitat on the unit by providing early successional habitats, food sources and cover for a variety of wildlife.
Location
The project areas are across the Mio District of the Huron National Forest, primarily west of M-33 in Big Creek Township
Project timeline
1
Scoping Start
04/06/2011
2
Comment Period
04/06/2011
3
Decision
11/2011 (Estimated)
4
Implementation
12/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Timber Sales (Green) |
| 2011 Mio Early Successional Project | Decision Signed Date: 11/07/2011 |
| Forests | Huron-Manistee National Forest |
| Districts | Mio Ranger District |
| Legal Land Description | T25N, R1W; T26N, R1W; T25N, R1E;T26N, R1E; T25N, R2E; T26N, R2E; T26N, R3E |