Construct trail to connect to a new staging area on land owned by the Newaygo Snowmobile Club and to bypass the M-20 trailhead. The new staging area is needed because the M-20 ORV trailhead has been paved and can no longer be used by snowmobiles.
Location
M-20 west 4 miles from White Cloud to M-20 Motorsport Trailhead (north side) and 1.75 miles west to new staging area and trail route north.
Project timeline
1
Scoping Start
06/30/2011
2
Decision
10/2011 (Estimated)
3
Implementation
12/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| M-20 Newaygo Snowmobile Trailhead and Reroute | Decision Signed Date: 10/20/2011 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District |