Amend Great Lakes Energy's existing special use permit to allow the installation of underground electric line in two locations. Both projects would provide power to private landowners.
Location
Sections 32-34, Pleasant Plains Township, Lake County and Section 25, Everett Township, Newaygo County
Project timeline
1
Scoping Start
03/28/2012
2
Comment Period
05/02/2012
3
Decision
09/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Special Use Authorization Amendment to Great Lakes Energy | Decision Signed Date: 09/10/2012 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District |