Project timeline

1
Scoping Start
05/04/2012
2
Comment Period
05/04/2012
3
Decision
08/2012 (Estimated)
4
Implementation
08/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
ALLBAND FIBER OPTIC CABLE PROJECT AMENDMENT #1Decision Signed Date: 08/20/2012
ForestsHuron-Manistee National Forest
DistrictsHuron Shores Ranger District
Legal Land DescriptionNW¼SW¼, SW¼SW¼, Section 5 and SW¼NW¼, NW¼SW¼, Section 8, T26N, R6E, Mitchell Township, Alcona County, Michigan
Special use management