Decision Memo Completed

Great Lakes Energy Amendment 2

Huron-Manistee National Forests Lake; Manistee; Mason; Wexford, Michigan Cadillac/Manistee Ranger District

Amend permit to combine GL Energy's permits across the Manistee NF and reissue Cadillac Manistee portion for a 30-year term (continued operation of electric distribution lines).

Location

44.3 acres in Wexford, Manistee, Lake, and Mason counties.

Project timeline

1
Scoping Start
12/24/2012
2
Decision
12/2015 (Estimated)
3
Implementation
12/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Great Lakes Energy Amendment 2Decision Signed Date: 12/03/2015
ForestsHuron-Manistee National Forest
DistrictsCadillac/Manistee Ranger District
Legal Land DescriptionWexford, Manistee, Lake, Mason Counties, Michigan
Special use management