The primary purpose of the Roy Creek Project is to create Kirtland's warbler essential breeding habitat within the Pine River KW Management Unit of the Huron National Forest.
Location
The project is located in both Iosco and Alcona Counties of Michigan. More specifically it is bordered by Cooke Pond to its south, east of M-65 and west of adjacent State Land.
Project timeline
1
Scoping Start
09/11/2014
2
Comment Period
09/30/2015
3
Objection Period Start
06/22/2016
4
Decision
09/2016 (Estimated)
5
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Species Population Enhancements; Road Maintenance; Timber Sales (Green); Watershed Improvements |
| Roy Creek Decision Notice | Decision Signed Date: 09/08/2016 |
| Forests | Huron-Manistee National Forest |
| Districts | Huron Shores Ranger District |
| Legal Land Description | T24N R7E S. 1-10, 15; T24N R6E S. 1-3, 10-12; T25N R6E S. 25, 35, 36; T 25N R7E S. 19-36 |