Decision Memo Completed

Great Lakes Energy Rebuild Project. Permit Amendment 4

Huron-Manistee National Forests Manistee, Michigan Cadillac/Manistee Ranger District

Realignment of existing buried powerline. Existing deteriorated line, 2500' of buried line through wooded area between 12 Mile Rd and Michael Rd, will be abandoned in place. New buried line will be along Seaman Rd and Sand Lake Dr.

Location

Norman Township, Manistee County, Michigan

Project timeline

1
Scoping Start
05/22/2014
2
Decision
08/2017 (Estimated)
3
Implementation
09/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Great Lakes Energy Rebuild Project. Permit Amendment 4Decision Signed Date: 08/04/2017
ForestsHuron-Manistee National Forest
DistrictsCadillac/Manistee Ranger District
Legal Land DescriptionT21N, R13W, Section 31
Special use management