Change of ownership and extending the term of lease for communication site at Harrietta.
Location
Harrietta Communication Site
Project timeline
1
Scoping Start
03/04/2015
2
Decision
03/2015 (Estimated)
3
Implementation
04/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Chesapeake Media 1, LLC | Decision Signed Date: 03/24/2015 |
| Forests | Huron-Manistee National Forest |
| Districts | Cadillac/Manistee Ranger District |
| Legal Land Description | part of the NW 1/4, Section 25, T22N, R12W, Slagle Township, Wexford County, Michigan |