This project proposes creation of fish structures and stream bank stabilization of up to twenty sites along the Pine River in Alcona County, Michigan. Stabilization of the erosion sites would reduce sediment delivery and improve aquatic habitat.
Location
Buhl Dam to Cruzin Road
Project timeline
1
Scoping Start
03/04/2015
2
Decision
08/2015 (Estimated)
3
Implementation
09/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| 2015 Pine River Bank Stabilization Project | Decision Signed Date: 08/26/2015 |
| Forests | Huron-Manistee National Forest |
| Districts | Huron Shores Ranger District |
| Legal Land Description | T25N, R8E, Section 7, 8, and 9. |