Environmental Assessment Completed

Martin Marietta Brine Pipeline Construction

Huron-Manistee National Forests Mason, Michigan Cadillac/Manistee Ranger District

Construction of a new brine pipeline, and construction of a temporary access road to allow equipment to access the construction site. Removal of a gate that is no longer needed and reissue the permit for the existing brine line.

Location

Mason County, Grand Township, T20N, R17W, Sec. 26 and 27

Project timeline

1
Scoping Start
05/07/2015
2
Comment Period
10/25/2016
3
Objection Period Start
06/06/2017
4
Decision
08/2017 (Estimated)
5
Implementation
08/2017 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Martin Marietta Brine Pipeline ConstructionDecision Signed Date: 08/04/2017