Cut oak trees in the Recreation site to remove dead and dying oak trees and prevent spread of oak wilt and thin red pine. Upto 70 acres will be treated.
Location
T24N, R5E section 11 in the South Branch Trail Camp
Project timeline
1
Scoping Start
10/07/2015
2
Decision
11/2015 (Estimated)
3
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage); Timber Sales (Green) |
| South Branch Trail Camp CE | Decision Signed Date: 11/30/2015 |
| Forests | Huron-Manistee National Forest |
| Districts | Huron Shores Ranger District |
| Legal Land Description | Not Applicable |