Construction of a new buried electrical transmission line along the west side of Irons Road, to be installed via plowing. The line will provide electrical service to nearby private property.
Location
Lake County, Eden township, T20N R13W, Section 19
Project timeline
1
Scoping Start
12/03/2015
2
Decision
04/2016 (Estimated)
3
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Great Lakes Energy Irons Road | Decision Signed Date: 04/24/2016 |
| Forests | Huron-Manistee National Forest |
| Districts | Cadillac/Manistee Ranger District |
| Legal Land Description | Lake County, Eden Township, T20N R13W, Section 19 |