Decision Memo Completed

Zimowske Road Reconstruction Authorization

Huron-Manistee National Forests Oscoda, Michigan Mio Ranger District

to clear and authorize several additional road segments that will exceed the 66 feet ROW by an additional 40 feet on NF land, plus relocate a snowmobile driveway and the FS would construct 220 feet of new connector trail

Location

Project Location: Oscoda County, Michigan, Huron National Forest %u2013 Mio Ranger District, T25N, R2E, sections 3, 4, 5 T26N, R2E, sections 32, 34, 35, 36

Project timeline

1
Scoping Start
07/16/2015
2
Decision
09/2016 (Estimated)
3
Implementation
09/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Improvements/Construction
Zimowske Road Reconstruction AuthorizationDecision Signed Date: 09/15/2016
ForestsHuron-Manistee National Forest
DistrictsMio Ranger District
Legal Land DescriptionNot Applicable
Special use managementRoad management