To manage for forest products for the local community, hazardous fuels reduction, recreation facilities and roads, and wildlife habitat improvement and maintenance.
Location
Eastern Au Sable River area
Project timeline
1
Scoping Start
02/01/2019
2
Comment Period
05/01/2019
3
Objection Period Start
08/07/2019
4
Decision
09/2019 (Estimated)
5
Implementation
10/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Fuel Treatments (Non-Activity Fuels); Dispersed Recreation Mgmt.; Species Habitat Improvements; Travel Management; Timber Sales (Green) |
| River Road | Decision Signed Date: 09/30/2019 |
| Forests | Huron-Manistee National Forest |
| Districts | Huron Shores Ranger District |
| Legal Land Description | Not Applicable |