This project will remove the remnants of Red Shoulder Dam #1 and the Beechwood Impoundment to restore the flow of waters into natural channels and floodplains.
Location
Red Shoulder Dam #1 off of Curtisville Road southeast of Mio, MI
Project timeline
1
Scoping Start
01/02/2017
2
Decision
02/2018 (Estimated)
3
Implementation
03/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Red Shoulder Dam #1 and Beechwood Impoundment Removal | Decision Signed Date: 02/26/2018 |
| Forests | Huron-Manistee National Forest |
| Districts | Mio Ranger District |
| Legal Land Description | Not Applicable |