Replace gravel sidewalks from the parking area to the pavilion and to the trail system with concrete walkways and reconstruct approximately 500 feet of trail that connects the parking area with the boardwalk to make it accessible.
Location
The site is located in T14N, R13W (Lincoln Township) in the NE1/4 of Section 2 and T15N, R13W (Merrill Township) in the SE1/4 of Section 35.
Project timeline
1
Scoping Start
03/03/2017
2
Decision
03/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Loda Lake Site and Trail Improvements | Decision Signed Date: 03/24/2017 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District |
| Legal Land Description | Not Applicable |