GLE is proposing a new buried power line. It will be installed via boring on the north side of Six Mile Bridge Road, and on the west side of Nine Mile Bridge Road in Manistee County. Only minor vegetation trimming and brush removal will be required.
Location
Manistee County, Stronach Township, T21N R15W Sec 29
Project timeline
1
Scoping Start
03/29/2017
2
Decision
08/2017 (Estimated)
3
Implementation
10/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Six Mile Bridge Road Great Lakes Energy New Line | Decision Signed Date: 08/04/2017 |
| Forests | Huron-Manistee National Forest |
| Districts | Cadillac/Manistee Ranger District |
| Legal Land Description | Manistee County, Stronach Township, T21N R15W Sec 29 |